Actions
Task #2807
openImplement Configure command on board side - USB Tool
Task #2807:
Implement Configure command on board side - USB Tool
Files
Updated by Sunder Venugopal 5 months ago
- Follows Task #2806: Implement Event Driven State Machine added
Updated by Sunder Venugopal 5 months ago
- Precedes Task #2808: QA Sanity and Regression Testing added
Updated by Sunder Venugopal 5 months ago
- Due date changed from 22/12/2025 to 28/01/2026
- Start date changed from 18/12/2025 to 26/01/2026
Updated by Sunder Venugopal 5 months ago
- Due date changed from 28/01/2026 to 23/12/2025
- Start date changed from 26/01/2026 to 19/12/2025
Updated by Mohan Kashyap 4 months ago
- Status changed from New to Hold
On hold untill we finalise Message Formats
Updated by Mohan Kashyap 4 months ago
- Status changed from Hold to In Progress
Updated by Mohan Kashyap 4 months ago
- % Done changed from 0 to 50
- Estimated time set to 24:00 h
Need to test the code
Updated by Mohan Kashyap 4 months ago
- % Done changed from 50 to 80
If we enable the receive path in LWIP TCP, the Global Interrupts stop firing after some time.
Updated by Sunder Venugopal 2 months ago
- Due date changed from 23/12/2025 to 02/03/2026
Config command should be run over USB.
Updated by Sunder Venugopal about 2 months ago
- % Done changed from 80 to 100
Updated by Mohan Kashyap about 2 months ago
- Subject changed from Implement Configure command on board side to Implement Configure command on board side - USB Tool
- Due date changed from 02/03/2026 to 20/03/2026
- Start date changed from 19/12/2025 to 16/03/2026
- Estimated time changed from 24:00 h to 40:00 h
Implement the configure command over USB Tool
Updated by Mohan Kashyap about 2 months ago
- Due date changed from 20/03/2026 to 27/03/2026
Updated by Mohan Kashyap about 2 months ago
- Estimated time changed from 40:00 h to 80:00 h
Updated by Mohan Kashyap about 2 months ago
- % Done changed from 100 to 50
Updated by Thomas Joseph about 1 month ago
- Target version set to Future
Updated by Mohan Kashyap about 1 month ago
- Due date changed from 27/03/2026 to 02/04/2026
- Assignee changed from Mohan Kashyap to Prakash M
Updated by Mohan Kashyap 26 days ago
- % Done changed from 50 to 80
Implemented coding as per USB Tool.
The configuration parameters are updated from USB Tool
Need to apply the parameters and test
Actions
