Task #3022
closedTask #2992: Procurement
GW BoM Component Procurement
Task #3022:
GW BoM Component Procurement
Start date:
02/03/2026
Due date:
18/03/2026
% Done:
0%
Estimated time:
Updated by Thomas Joseph 4 months ago
- Status changed from New to In Progress
Components for 2 PCBs are in stock. pilot delivery - one unit
Need to order components in bulk (reel) for production.
Hence this task may be considered as resolved
Updated by Dhanasekar T 4 months ago
- % Done changed from 0 to 30
Updated by Thomas Joseph 4 months ago
- Status changed from In Progress to Hold
- % Done changed from 30 to 0
This task may be moved to production project. Hence marked as hold
Updated by Thomas Joseph 3 months ago
- Status changed from Hold to Closed
refer => http://5.161.106.25:3000/issues/3125
The task is closed