Task #3220
openTask #3196: Procurement
PLCIO BoM Component Procurement
Task #3220:
PLCIO BoM Component Procurement
Start date:
19/01/2026
Due date:
28/01/2026 (about 3 months late)
% Done:
40%
Estimated time:
Spent time:
Updated by Thomas Joseph 3 months ago
- Parent task set to #3196
Updated by Dhanasekar T 3 months ago
- % Done changed from 10 to 20
N58-CA-081AS1-40 nos (AT Command)
N58-CA-082AS1-10 nos (OpenCPU)
Received
Updated by Thomas Joseph 3 months ago
- Subject changed from GW & PLCIO BoM Component Procurement to PLCIO BoM Component Procurement
Updated by Dhanasekar T about 1 month ago
- % Done changed from 20 to 30
Initially 5 sets of components added in the cart.
Need to place order.
Updated by Dhanasekar T about 1 month ago
- % Done changed from 30 to 40
Order placed