Task #2912: Hardware Readiness

Added by Sunder Venugopal 2 months ago. Updated about 1 month ago.

Status:
Resolved
Priority:
Normal
Assignee:
Start date:
14/01/2026
Due date:
16/01/2026 (54 days late)
% Done:

100%

Estimated time:

Files

Image (2).jpeg (27.6 KB) Image (2).jpeg VenuMadhav S, 20/01/2026 08:28 AM
Image.jpeg (25.2 KB) Image.jpeg VenuMadhav S, 20/01/2026 08:28 AM
Image (1).jpeg (32.2 KB) Image (1).jpeg VenuMadhav S, 20/01/2026 08:28 AM
Image (2).jpeg
Image.jpeg
Image (1).jpeg

Related issues 2 (2 open0 closed)

Precedes Chola Turbo Machinery Pvt Ltd - Task #2917: System Test Results and Reports Analysis StartedJagatheswaran J22/01/202626/01/2026

Actions
Precedes Chola Turbo Machinery Pvt Ltd - Task #2959: Customer Demo - Internal ready ResolvedVenuMadhav S19/01/202627/01/2026

Actions

SV Updated by Sunder Venugopal 2 months ago Actions #1

  • Due date changed from 13/01/2026 to 14/01/2026

go with 80 X 120 X 55 mm for pilot.
90X 130 X 65 mm Final
Enclosure Development
Board Bring-up

SV Updated by Sunder Venugopal 2 months ago Actions #2

  • Precedes Task #2917: System Test Results and Reports added

TJ Updated by Thomas Joseph 2 months ago Actions #3

  • Start date changed from 02/01/2026 to 14/01/2026

SV Updated by Sunder Venugopal 2 months ago Actions #4

  • Precedes Task #2959: Customer Demo - Internal ready added

TJ Updated by Thomas Joseph about 2 months ago Actions #5

  • Due date changed from 14/01/2026 to 16/01/2026

Due to delay in

1. Box screen printing - design not yet completed => http://5.161.106.25:3000/issues/3017#note-4
2. Screen printing fabrication => 3days => http://5.161.106.25:3000/issues/3070

Due date extended to 16/01/2026

TJ Updated by Thomas Joseph about 2 months ago Actions #6

  • Start date changed from 14/01/2026 to 16/01/2026

TJ Updated by Thomas Joseph about 2 months ago Actions #7

  • Start date changed from 16/01/2026 to 14/01/2026

TJ Updated by Thomas Joseph about 2 months ago Actions #8

1. PCB Assembly completed and integrated including LED PCB
2. Unit assembled in sample enclosure

The unit is ready for testing now

Once the final enclosure is ready, the PCB unit will be transferred to that.

TJ Updated by Thomas Joseph about 2 months ago Actions #9

  • Status changed from Analysis Started to In Progress
  • % Done changed from 0 to 80

VS Updated by VenuMadhav S about 2 months ago Actions #10

Image (1).jpeg
Image (2).jpeg
Image.jpeg

Assembled the PCB's and Product is handed over to Embedded software development team

TJ Updated by Thomas Joseph about 2 months ago Actions #11

  • % Done changed from 80 to 90

TJ Updated by Thomas Joseph about 2 months ago Actions #12

  • % Done changed from 90 to 100

TJ Updated by Thomas Joseph about 1 month ago Actions #13

  • Status changed from In Progress to Resolved