Issues
| open | closed | Total | |
|---|---|---|---|
| Assigned issues | 82 | 5 | 87 |
| Reported issues | 12 | 0 | 12 |
Projects
| Project | Roles | Registered on |
|---|---|---|
| Gateway 3.0 | HW_Lead | 25/02/2026 |
| Chola Turbo | HW_Lead | 02/01/2026 |
| mDAQ4-1(Mid Range mDAQ)-Pilot | Manager, Hardware Engr. | 06/01/2026 |
| mDAQ4-1(Mid Range mDAQ)-Production | Manager, Hardware Engr. | 09/01/2026 |
| mTracker(Mid Range GW)-Pilot | Manager, Hardware Engr. | 06/01/2026 |
| mTracker(Mid Range GW)-Production | Manager, Hardware Engr. | 09/01/2026 |
| Gateway V2 | Manager | 24/12/2025 |
| Gateway V2.1 | Manager | 24/12/2025 |
| SAMA5D4 Hardware Development | HW_Lead | 27/03/2026 |
| VAS Product Release 2.0 | Manager | 09/12/2025 |
Activity
20/04/2026
-
11:02 AM VAS Product Release 2.0 Task #3392: Project Planning and Review
- 1. Face Plate Design.
2. Panel Assembly.
3. mDAQ3(V1.1) PCB Testing.
08/04/2026
-
06:22 AM VAS Product Release 2.0 Task #3436 (Analysis Done): Pre-Installation Visit
- https://elpisit-my.sharepoint.com/:w:/g/personal/satish_sl_elpisitsolutions_com/IQDLLyN_get9QLdW1aWUPyCxAb-tO7y27yhZIEB14KaYzX4?e=FTiNn1
-
05:26 AM VAS Product Release 2.0 Task #3413 (Closed): PCB Revision and Gerber release
-
05:26 AM VAS Product Release 2.0 Task #3413: PCB Revision and Gerber release
- https://elpisit-my.sharepoint.com/:u:/g/personal/satish_sl_elpisitsolutions_com/IQCmcouK5DTnTaavtwoXS1WVAR8uL5ztz3TbT1eEHDT6Llw?e=WARlyY
Gerber File -
05:21 AM VAS Product Release 2.0 Task #3409: Performance check with LAN
- Switch Provided to do Performance check with LAN.
27/03/2026
-
02:09 PM VAS Product Release 2.0 Task #3413 (Analysis Done): PCB Revision and Gerber release
- https://elpisit-my.sharepoint.com/:x:/g/personal/satish_sl_elpisitsolutions_com/IQAYa463aQmvRov_X2jOW3whAYDpzmS0Qq5xebsJFpNuNE4?e=EcJ7LG
Updated Rework sheet.
24/03/2026
-
11:26 AM Gateway 3.0 Task #3330: Enclosure Design
- If we are using single PCB. Need to be find new enclosure.
-
11:25 AM Gateway 3.0 Task #3330 (In Progress): Enclosure Design
23/03/2026
-
06:14 AM VAS Product Release 2.0 Task #3380: Hardware Readiness - Synchronous RPM
- Set up was handed over to Software development.
-
06:09 AM Chola Turbo Task #2944 (Resolved): Assembly