Task #2938
openTask #2942: Procurement
Enclosure fabrication
100%
Updated by Thomas Joseph 4 months ago
- Description updated (diff)
Updated by Thomas Joseph 4 months ago
- Is duplicate of Task #2940: Enclosure fabrication added
Updated by Thomas Joseph 4 months ago
- Parent task set to #2942
Updated by Thomas Joseph 4 months ago
- Assignee changed from VenuMadhav S to Dhanasekar T
Updated by Dhanasekar T 4 months ago
- % Done changed from 0 to 30
sent design file to supplier for fabrication.
Updated by Dhanasekar T 4 months ago
- % Done changed from 30 to 50
Fabrication process started
1.SRS enterprises-2 nos
2.Polymer craft-5 nos
Will expect on monday (12-01-2026)
Updated by Thomas Joseph 4 months ago
- Status changed from Analysis Started to Resolved
- % Done changed from 50 to 100
Enclosure procured and moved to fabricator
Updated by Thomas Joseph 4 months ago
- Status changed from Resolved to In Progress
- % Done changed from 100 to 50
Updated by Thomas Joseph 4 months ago
· Edited
Received sample enclosure with cut-outs, w/o screen printing from (Lathe.... fill company name). The final box is expected on 16/01/2026
Updated by Thomas Joseph 4 months ago
- Due date changed from 12/01/2026 to 16/01/2026
Updated by VenuMadhav S 4 months ago
After USB, Ethernet, Interface connector Cutout's validation.
Design was updated and shared to fabricator over phone.
Expected receiving the enclosure date with screen printing is 16-01-2026.
Updated by Thomas Joseph 4 months ago
Please share updated design and updated observations
Updated by VenuMadhav S 4 months ago
Due to the Continuous pongal festival holidays. From the fabricator it got delayed.
Today we are expecting the enclosure with cut outs and screen printing.
Updated by Dhanasekar T 4 months ago
Machining and laser marking completed for chola and core4-mTracker.
It is coming through porter
Updated by Thomas Joseph 3 months ago
· Edited
- % Done changed from 50 to 100
Fabrication completed and received boxes from Polymer craft.
@Dhanasekar T : Update quality check report
Updated by Dhanasekar T 3 months ago
Quality check report document updated
Updated by Thomas Joseph 3 months ago
- Status changed from In Progress to Resolved