Project

General

Profile

Actions

Task #2991

open

Task #2985: Detailed Design

Wiring Diagram

Task #2991: Wiring Diagram

Added by Thomas Joseph 4 months ago. Updated about 1 month ago.

Status:
In Progress
Priority:
Normal
Assignee:
Target version:
-
Start date:
29/04/2026
Due date:
30/04/2026 (4 days late)
% Done:

50%

Estimated time:

Related issues 2 (2 open0 closed)

Follows mDAQ4-1(Mid Range mDAQ)-Pilot - Task #2989: Embedded SW-DevelopmentNew20/03/202628/04/2026

Actions
Follows mDAQ4-1(Mid Range mDAQ)-Pilot - Task #3042: Test Plan Development and ApprovalsIn ProgressJagatheswaran J08/04/202615/04/2026

Actions

Updated by Thomas Joseph 4 months ago Actions #1

In orcad, use the BD of GW2.0, add LED PCB and IO-USB as a block and show interconnections.

For stacking, use block arrows

Updated by Thomas Joseph 3 months ago Actions #3

  • Due date changed from 06/01/2026 to 23/01/2026
  • Status changed from New to In Progress
  • % Done changed from 0 to 50

Wiring completed. Need to document in ISO template

Due date extended to 23/01/2026

Updated by Sunder Venugopal about 2 months ago Actions #4

  • Due date changed from 08/04/2026 to 18/05/2026
  • Start date changed from 20/03/2026 to 29/04/2026
  • Follows Task #2989: Embedded SW-Development added

Updated by Sunder Venugopal about 2 months ago Actions #5

  • Follows Task #3042: Test Plan Development and Approvals added

Updated by Sunder Venugopal about 2 months ago Actions #6

  • Due date changed from 18/05/2026 to 30/04/2026
Actions

Also available in: PDF Atom