Actions
Task #3047
openTask #2934: Detailed Design
Review/Update of GW2.0 Test Plan and Procedure
Task #3047:
Review/Update of GW2.0 Test Plan and Procedure
Start date:
09/01/2026
Due date:
13/01/2026 (about 4 months late)
% Done:
100%
Estimated time:
Description
Review GW2.0 TPP, add new stages for USB, IO sections
Updated by VenuMadhav S 3 months ago
- Status changed from New to In Progress
- % Done changed from 0 to 90
Updated by Thomas Joseph 3 months ago
- Status changed from In Progress to Resolved
- % Done changed from 90 to 100
Reviewed