Task #3156

open

Task #2985: Detailed Design

Task #2989: Embedded SW-Development

Hardware Setup readiness for software development

Task #3156: Hardware Setup readiness for software development

Added by Thomas Joseph 4 months ago. Updated about 1 month ago.

Status:
Resolved
Priority:
Normal
Target version:
-
Start date:
20/03/2026
Due date:
24/03/2026 (41 days late)
% Done:

100%

Estimated time:
Spent time:

Description

Interface PLCIO with Gateway using Cable connection


Files

Media (8).jpg (87.1 KB) Media (8).jpg Dhilip Kumar R, 21/01/2026 07:27 AM
Media (8).jpg

Updated by Thomas Joseph 4 months ago Actions #1

  • Due date changed from 19/01/2026 to 20/01/2026
  • Start date changed from 16/01/2026 to 20/01/2026

Updated by Thomas Joseph 4 months ago Actions #2

  • Assignee changed from VenuMadhav S to Resmi K.V

Updated by Thomas Joseph 4 months ago Actions #3

  • Due date changed from 20/01/2026 to 19/01/2026
  • Start date changed from 20/01/2026 to 19/01/2026

Updated by Sumanth D 4 months ago Actions #4

  • Assignee changed from Resmi K.V to Sumanth D

Updated by Thomas Joseph 4 months ago · Edited Actions #5

Interface GW2.0 with PLCIO.
assemble the setup(GW2.0 and PLCIO) in a Hylam sheet, fix debugger also so that S/W team need not access the hardware physically. Arrange test setup also beside this.

All in a single Hylam sheet,compact, convenient for SW development

Refer architecture => http://5.161.106.25:3000/issues/2984#note-4

Updated by Sumanth D 3 months ago · Edited Actions #6

  • Status changed from New to In Progress
  • % Done changed from 0 to 20

Updated by Sumanth D 3 months ago · Edited Actions #7

  • Assignee changed from Sumanth D to Dhanasekar T

Need to assemble PLCIO and GWV2 in a Hylam sheet by connecting the Debugger and Test setup of AI, AV, DI and DO

Please complete this with the help of Dhilip by today

Updated by Thomas Joseph 3 months ago · Edited Actions #8

  • Due date changed from 19/01/2026 to 21/01/2026

Due date extended due to delay in assembled GW PCB (http://5.161.106.25:3000/issues/2997)

Updated by Sumanth D 3 months ago Actions #10

  • Assignee changed from Dhanasekar T to Sumanth D

Updated by Sumanth D 3 months ago Actions #11

  • % Done changed from 20 to 40

Updated by Sumanth D 3 months ago Actions #12

  • Assignee changed from Sumanth D to Dhilip Kumar R

Updated by Dhilip Kumar R 3 months ago · Edited Actions #13

Media (8).jpg

The single Hylam sheet, assemble the setup for PLCIO and Test setup of AI, AV, DI and DO.
!Media%20%288%29.jpg!
Waiting to GWV2 PCB.

Updated by Thomas Joseph 3 months ago Actions #14

  • Status changed from Resolved to In Progress

Updated by Thomas Joseph 3 months ago Actions #15

  • Status changed from In Progress to Resolved
  • % Done changed from 80 to 100

30/01/2026
GW PCB integrated and unit is ready for development