Task #3191
openTask #3045: Detailed Design
Task #3189: Design and Development of PLCIO PCB
PCB Design
Updated by Thomas Joseph 3 months ago
- Parent task set to #3189
Updated by Thomas Joseph 3 months ago
- Due date changed from 24/01/2026 to 28/01/2026
- Status changed from New to In Progress
- % Done changed from 10 to 0
Updated by Thomas Joseph 3 months ago
- Assignee set to VenuMadhav S
Updated by Thomas Joseph 3 months ago
- Due date changed from 28/01/2026 to 17/02/2026
- Status changed from In Progress to New
- Assignee changed from VenuMadhav S to Thomas Joseph
- Start date changed from 20/01/2026 to 02/02/2026
Due Date extended
Updated by Thomas Joseph 3 months ago
- Assignee changed from Thomas Joseph to Resmi K.V
import to board (GW2.2 controller), add missing footprints, initiate placements
Updated by Thomas Joseph 3 months ago
- Status changed from New to In Progress
- % Done changed from 0 to 40
Updated by Resmi K.V 3 months ago
· Edited
- % Done changed from 40 to 60
As per the placement plan created, from the updated schematic all the component are placed except the input connectors. the placement need to review and then will do the final placement and routing.
DSN folder is uploaded in onedrive: https://elpisit-my.sharepoint.com/:u:/g/personal/satish_sl_elpisitsolutions_com/IQBKWs8VjfMQQbqIlkOdhwO2AS2EIaV6ctoNABYo5W7N08g?e=9qVLRl
Updated by Resmi K.V 2 months ago
- % Done changed from 60 to 70
Schematic updated. and uploaded in onedirve. kindly check it.
DSN folder: https://elpisit-my.sharepoint.com/:u:/g/personal/satish_sl_elpisitsolutions_com/IQABw6ez1mgeSYszeM0-PEmMASZwoaR-P6_egVx6UgPEjzE?e=b4KCh6
Updated by Resmi K.V 2 months ago
As per the discussion made with Thomas sir, Schematic updated.
1.Daisy chaining is added for DI
2.LDO provided for AI supply.
3.Created netlist and imported to board and all the components are placed.
4.DO section 3 connections are pending.
Updated DSN folder uploaded in onedrive.
https://elpisit-my.sharepoint.com/:u:/g/personal/satish_sl_elpisitsolutions_com/IQBZGCOz2mF5TqXtTGFt-ZYbATANUBGfBQPTR9cQeYlXbtk?e=ni8oU2
Updated by Resmi K.V 2 months ago
Ground in all the sections(AI,DI,DO) seperated.
Back annotation done .
routing is in progress.
Updated Design uploaded in onedrive. https://elpisit-my.sharepoint.com/:u:/g/personal/satish_sl_elpisitsolutions_com/IQCfabk4mw9JRaKyiyXwJGaTASq5y-7WCxtrnrO3CqvhY5Y?e=DBVPFE
Updated by Resmi K.V 2 months ago
PCB routing is in progress. Gnd Plane to be discussed with thomas sir.
Updated design uploaded in onedrive.
https://elpisit-my.sharepoint.com/:u:/g/personal/satish_sl_elpisitsolutions_com/IQCEj3jCUe_wS4lCTlGiNN5zAa13Rh3HOtX7F5vSi4tD4SU?e=F7aktG
Updated by Resmi K.V about 2 months ago
Updated the board file (smoothening of traces and GND plane extended). please review this latest board file which is uploaded in onedrive.
Updated by Resmi K.V about 2 months ago
PLCIO V2P0 board file updated and uploaded in onedrive
dsn folder: https://elpisit-my.sharepoint.com/:u:/g/personal/satish_sl_elpisitsolutions_com/IQBb5FaE5K_qSKTWnp7PG05MAf3tiWWNGAl8HJgnH52nEds?e=XShPdu
Updated by Resmi K.V about 2 months ago
Board file updated.step file created and shared to Venumadhav .
updated design uploaded in onedrive: https://elpisit-my.sharepoint.com/:u:/g/personal/satish_sl_elpisitsolutions_com/IQBTNo-JfoltT7sW9aC_WRo-AftvJRapK4gvhBWIkRURyII?e=aHZwyk
Updated by Resmi K.V about 1 month ago
- % Done changed from 80 to 90