Task #3302

open
TJ VK

Customer Requirements Finalisation

Task #3302: Customer Requirements Finalisation

Added by Thomas Joseph 14 days ago. Updated 12 days ago.

Status:
In Progress
Priority:
Normal
Start date:
09/02/2026
Due date:
20/02/2026 (19 days late)
% Done:

0%

Estimated time:

TJ Updated by Thomas Joseph 14 days ago Actions #1

  • Project changed from 5 to Gateway 3.0

TJ Updated by Thomas Joseph 12 days ago Actions #2

  • Due date set to 20/02/2026
  • Priority changed from Urgent to Normal
  • Start date set to 09/02/2026
  • % Done changed from 90 to 50

TJ Updated by Thomas Joseph 12 days ago Actions #3

  • % Done changed from 50 to 0