Task #3520:
Mechanical Fabrication
Start date:
20/04/2026
Due date:
09/06/2026 (about 3 months late)
% Done:
100%
Estimated time:
Spent time:
Actions
Added by Thomas Joseph 5 months ago. Updated 3 months ago.
100%
Inform Venu sir about V300 design
Initiate with Deeksha
Due date changed from 20/04/2026 to 03/06/2026
Due date extended based on http://5.161.106.25:3000/issues/3662#note-1
Meeting discussion (VM, DT, BSN)
-Check waveshare display, depth, availability, order if we get in this week
-followup Top plate design with Shiva
-update bottom plate design
---use actual size of all components, boxes
---add cable entry for all, with bending radius, mini pc fins
---fix mini pc direction
---consider an exhaust fan
---ISP box add in design
-Decide clamp after completing the bottom plate design
9/06/2026
Clamp fab completed
18/06/2026
Top plate fabrication completed and received
All fabrication completed