Hours: 24:00

Date User Activity Issue Comment Hours Status Author Project Created Target version Tracker Week Category Finish Date Start Date Engr, %effort Team_Size Severity
02/01/2026 Channamallikarjuna Mattihalli Development Task #2873: 4G Implimentation as asyncronous or nonblocking way Kept for Testing since 31-12-2025 8:00 In Progress Channamallikarjuna Mattihalli Gateway V2 02/01/2026 04:57 AM Task 1 31/03/2026 18/06/2025 Channa 100%, VenuM 30%, Greeshma 30%, Gowri 20%, Bhavani 50% 2 Actions
31/12/2025 Channamallikarjuna Mattihalli Development Task #2873: 4G Implimentation as asyncronous or nonblocking way The data is posting on the dashboard 8:00 In Progress Channamallikarjuna Mattihalli Gateway V2 31/12/2025 07:02 AM Task 1 31/03/2026 18/06/2025 Channa 100%, VenuM 30%, Greeshma 30%, Gowri 20%, Bhavani 50% 2 Actions
31/12/2025 Channamallikarjuna Mattihalli Development Task #2873: 4G Implimentation as asyncronous or nonblocking way 4G interface with non blocking way 8:00 In Progress Channamallikarjuna Mattihalli Gateway V2 31/12/2025 05:32 AM Task 1 31/03/2026 18/06/2025 Channa 100%, VenuM 30%, Greeshma 30%, Gowri 20%, Bhavani 50% 2 Actions
    (1-3/3)

    Also available in: CSV Atom