Hours: 1:00

Date User Activity Issue Comment Hours Status Author Project Created Target version Tracker Week Category Finish Date Start Date Engr, %effort Team_Size Severity
12/01/2026 Thomas Joseph Design Task #3069: Preliminary Design System Study and Design Plan 1:00 In Progress Thomas Joseph mTracker(Mid Range GW)-Production 13/01/2026 04:25 AM Task 3 31/03/2026 02/01/2026 Thomas(30%), Venumadhav(100%),Dhilip(20%) 3 Actions