Hours: 5:00

Project Date User Activity Issue Comment Hours Status Author Created Target version Tracker Week Category Finish Date Start Date Engr, %effort Team_Size Milestone Reference Critical Path Severity
VAS Product Release 2.0 14/05/2026 Thomas Joseph Development Task #3414: mDAQ3 Customisation for ISTRAC mDAQ3 Integration 2:00 In Progress Thomas Joseph 25/06/2026 04:40 AM VAS Product Release 2.0 - RHMS-ISTRAC Task 20 19/03/2026 01/12/2025 Mohan 100% 1 Actions
VAS Product Release 2.0 11/05/2026 Thomas Joseph Development Task #3417: Faceplate Fabrication Faceplate Review 1:00 In Progress Thomas Joseph 25/06/2026 03:46 AM VAS Product Release 2.0 - RHMS-ISTRAC Task 20 19/03/2026 01/12/2025 Mohan 100% 1 Actions
VAS Product Release 2.0 08/05/2026 Thomas Joseph Development Task #3416: Faceplate Design Faceplate requirements and design 2:00 In Progress Thomas Joseph 25/06/2026 03:26 AM VAS Product Release 2.0 - RHMS-ISTRAC Task 19 19/03/2026 01/12/2025 Mohan 100% 1 Actions
    (1-3/3)