General

Profile

Surendra Naik

  • Login: Surendra
  • Registered on: 31/01/2024
  • Last sign in: 28/04/2026

Issues

open closed Total
Assigned issues 21 0 21
Reported issues 0 0 0

Projects

Project Roles Registered on
Customer RMA, AMC & SERVICE Hardware Engr. 21/01/2026
Gateway 3.0 Hardware Engr. 25/02/2026
Chola Turbo Hardware Engr. 13/01/2026
mDAQ4-1(Mid Range mDAQ)-Pilot Hardware Engr. 06/01/2026
mDAQ4-1(Mid Range mDAQ)-Production Hardware Engr. 19/01/2026
mTracker(Mid Range GW)-Pilot Hardware Engr. 09/01/2026
mTracker(Mid Range GW)-Production Hardware Engr. 19/01/2026
Gateway V2.1 Hardware Engr. 24/12/2025
SAMA5D4 Platform Hardware Engr. 27/03/2026
SAMA5D4 Hardware Development Hardware Engr. 23/12/2025
TPMS 2-Wheeler Hardware Engr. 23/12/2025
TPMS 4 Wheeler Hardware Engr. 29/12/2025

Activity

25/03/2026

06:00 AM Gateway 3.0 Task #3453 (In Progress): SMA connector replace N58 EVM
Surendra Naik
05:58 AM Gateway 3.0 Task #3286 (In Progress): Hardware Setup readiness for software development
Surendra Naik

02/03/2026

12:03 PM Gateway 3.0 Task #3337 (Resolved): TV2.1 Hardware Readiness
I removed the GPS module from the V2P1 tracker board and placed a UART to RS232 module in the same place, then connected the circuit. I also checked and verified the RS232 to UART connector connection at the external connector. Surendra Naik
12:03 PM Gateway 3.0 2:00 hours (Task #3337 (Resolved): TV2.1 Hardware Readiness)
rs232 module placement Surendra Naik
09:28 AM Gateway 3.0 Task #3337 (In Progress): TV2.1 Hardware Readiness
Surendra Naik

26/02/2026

12:24 PM mDAQ4-1(Mid Range mDAQ)-Pilot 8:00 hours (Task #3261 (In Progress): RTU Cable for DI, DO, AI)
cable assembly for RTU Surendra Naik
12:24 PM mDAQ4-1(Mid Range mDAQ)-Pilot Task #3261: RTU Cable for DI, DO, AI
For the RTU cable (DI, DO, AI), I prepared 1-meter length wiring with a D-sub connector.
Now testing is pending.
Surendra Naik

19/02/2026

08:03 AM mTracker(Mid Range GW)-Pilot 4:00 hours (Task #2979 (In Progress): Hardware Readiness)
GW mcu board testing & rework Surendra Naik
08:03 AM mTracker(Mid Range GW)-Pilot Task #2979: Hardware Readiness
3 set boards that came from the assembly house, I completed rework and mounted the DNP components and TH connectors on the 1set MCU, 4G, and Wi-Fi boards. Surendra Naik

18/02/2026

12:07 PM mDAQ4-1(Mid Range mDAQ)-Pilot Task #3159 (Resolved): PLCIO Interface Cable
PLCIO Interface Cable PREPARATION COMPLTED Surendra Naik