Task #2947
openTask #2944: Assembly
Mechanical Assembly
Added by Thomas Joseph 2 months ago. Updated about 1 month ago.
TJ Updated by Thomas Joseph 2 months ago Actions #1
- Assignee changed from VenuMadhav S to Dhanasekar T
TJ Updated by Thomas Joseph about 2 months ago Actions #2
1.Stack Controller and 4G PCB to match the cutouts
2.Assemble the USB PCB and check enclosure cutout matching
3.Complete wiring
TJ Updated by Thomas Joseph about 2 months ago · Edited Actions #3
Due date extened to 16/01/2026 due to delay in
http://5.161.106.25:3000/issues/2938
http://5.161.106.25:3000/issues/3071
TJ Updated by Thomas Joseph about 2 months ago Actions #4
- Due date changed from 13/01/2026 to 16/01/2026
DT Updated by Dhanasekar T about 2 months ago Actions #5
- Status changed from New to In Progress
- % Done changed from 0 to 50
TJ Updated by Thomas Joseph about 2 months ago Actions #6
1. http://5.161.106.25:3000/issues/2933 => Upload step file in onedrive and share link
2. Update all issues with enclosure in http://5.161.106.25:3000/issues/2947#note-5
3. Share Photo of the corrected assembly - Connector misalignment, LED PCB
4. Update all rework in the design, generate new PCB and step file
TJ Updated by Thomas Joseph about 2 months ago · Edited Actions #7
- % Done changed from 50 to 90
14/01/2026
Assembly completed in sample enclosure.
The PCB unit will be transferred into the final enclosure on 16/01/2026 (expected the enclosure from fabricator )
Note
1. Mount LED PCB also, glue it to lid so that this unit will be ready
2. Share photos
a. PCB unit from all sides
b. the enclosure inside, top lid.
c. Inside, just before closing and screwing lid
3. When new enclosure comes, fix a new LED PCB in that and transfer the PCB unit
SV Updated by Sunder Venugopal about 2 months ago Actions #8
- Related to Task #2946: USB PCB Assembly added
SV Updated by Sunder Venugopal about 2 months ago Actions #9
- Related to deleted (Task #2946: USB PCB Assembly)
SV Updated by Sunder Venugopal about 2 months ago Actions #10
- Due date changed from 19/01/2026 to 20/01/2026
- Start date changed from 14/01/2026 to 15/01/2026
- Follows Task #2946: USB PCB Assembly added
TJ Updated by Thomas Joseph about 2 months ago · Edited Actions #11
Dhanasekar T wrote in #note-5:
Mechanical assembly observations
Updated assembly observations => https://elpisit-my.sharepoint.com/:x:/g/personal/satish_sl_elpisitsolutions_com/IQDyLHjCl5lERKGKEN6lDhRcAavszsjhbJCkh9dLz4DTWCI?e=VE3X6B
TJ Updated by Thomas Joseph about 2 months ago Actions #12
- Follows deleted (Task #2946: USB PCB Assembly)
TJ Updated by Thomas Joseph about 2 months ago Actions #13
- % Done changed from 90 to 100
TJ Updated by Thomas Joseph about 2 months ago Actions #14
Take photographs of
bottom cover inside and outsides, top lid (w/ LED PCB mounted) inside and outside
PCB integrated unit from all sides w/o tilt or cut in white background
after inserting into the bottom cover
after screwing with top lid
Product photo with antenna mounted suitable angle for making brochure
TJ Updated by Thomas Joseph about 1 month ago Actions #15
- Status changed from In Progress to Resolved