Task #2997
openTask #2992: Procurement
GW 2.0 PCB Assembly
Added by Thomas Joseph 2 months ago. Updated about 1 month ago.
DT Updated by Dhanasekar T 2 months ago Actions #1
- Status changed from New to In Progress
- % Done changed from 0 to 30
BoM sent to uV for quotation.
2 sets of components in stock.
Remaining 3 sets of components needs to be order and I added in the cart.
PR created and sent to venu sir for approval.
As per thomas sir suggestion,need to wait for bulk order.
DT Updated by Dhanasekar T 2 months ago Actions #2
- % Done changed from 30 to 50
2 sets of components sent to uV for PCB assembly.
TJ Updated by Thomas Joseph about 2 months ago · Edited Actions #3
@VenuMadhav S : X-Y data from panel will change reference. Hence, create X-Y data for individual PCBs and mention the reference(origin) in Panel
DT Updated by Dhanasekar T about 2 months ago · Edited Actions #4
2 sets of board sent to uV for assembly
X & Y data sent to uV.
TJ Updated by Thomas Joseph about 2 months ago Actions #5
Expecting assembled PCB on Tuesday(20/01/2026)
DT Updated by Dhanasekar T about 2 months ago Actions #6
Today only they are receiving the stencil.
Informed to uV vinod sir for urgency.
TJ Updated by Thomas Joseph about 2 months ago Actions #7
- Due date changed from 16/01/2026 to 21/01/2026
Expecting the assembled PCB today . Due date extended
TJ Updated by Thomas Joseph about 2 months ago Actions #8
- % Done changed from 50 to 80
DT Updated by Dhanasekar T about 2 months ago Actions #9
uV vinod sir committed today 1 set of PCB will dispatch
2nd set of PCB tomorrow.
TJ Updated by Thomas Joseph about 2 months ago Actions #10
- Due date changed from 21/01/2026 to 23/01/2026
Due date extended
DT Updated by Dhanasekar T about 2 months ago Actions #11
- % Done changed from 80 to 90
Assembly is completed
Qc is inprogress.
DT Updated by Dhanasekar T about 2 months ago Actions #12
2 sets of Assembled board received
DT Updated by Dhanasekar T about 1 month ago Actions #13
- Status changed from In Progress to Resolved
- % Done changed from 90 to 100
PCB assembly completed and received at our end