Task #3005
openSystem Testing
Task #3005:
System Testing
Start date:
11/05/2026
Due date:
25/05/2026 (Due in 21 days)
% Done:
0%
Estimated time:
Updated by Thomas Joseph 4 months ago
- Assignee changed from VenuMadhav S to Jagatheswaran J
Updated by Thomas Joseph 3 months ago
- Due date changed from 22/01/2026 to 29/01/2026
- Start date changed from 21/01/2026 to 27/01/2026
Due date extended due to delay in Mech. fab & assembly
Updated by Thomas Joseph 3 months ago
Start the system test w/o PCB assembled in enclosure due to delay in http://5.161.106.25:3000/issues/2993#note-4
Updated by Thomas Joseph 3 months ago
- Due date changed from 29/01/2026 to 16/02/2026
++ @Gowri G G
@Jagatheswaran J J : Please make the test case document available for @Gowri G G to use for testing
Updated by Sunder Venugopal about 2 months ago
- Due date changed from 16/02/2026 to 30/04/2026
Updated by Sunder Venugopal about 2 months ago
- Due date changed from 30/04/2026 to 03/08/2026
- Start date changed from 27/01/2026 to 30/04/2026
- Follows Task #2990: E-REMOS Development added
Updated by Sunder Venugopal about 2 months ago
- Precedes Task #3007: Customer Demo added
Updated by Sunder Venugopal about 2 months ago
- Precedes Task #3008: Delivery (Pilot) added
Updated by Sunder Venugopal about 2 months ago
- Precedes deleted (Task #3008: Delivery (Pilot))
Updated by Sunder Venugopal about 2 months ago
- Due date changed from 03/08/2026 to 06/11/2026
- Start date changed from 30/04/2026 to 05/08/2026
- Follows Task #3008: Delivery (Pilot) added
Updated by Sunder Venugopal about 2 months ago
- Due date changed from 06/11/2026 to 12/08/2026
- Start date changed from 05/08/2026 to 11/05/2026
Updated by Sunder Venugopal about 2 months ago
- Parent task deleted (
#3004)
Updated by Sunder Venugopal about 1 month ago
- Due date changed from 12/08/2026 to 25/05/2026
Updated by Jagatheswaran J about 1 month ago
- % Done changed from 0 to 80
Updated by Jagatheswaran J about 1 month ago
- % Done changed from 80 to 0