Project

General

Profile

Actions

Task #3662

open

Project Planning and Review

Task #3662: Project Planning and Review

Added by Thomas Joseph 3 months ago. Updated 3 months ago.

Status:
In Progress
Priority:
Normal
Assignee:
Target version:
Start date:
01/04/2026
Due date:
30/06/2026 (about 2 months late)
% Done:

90%

Estimated time:
Spent time:

Updated by Thomas Joseph 3 months ago · Edited Actions #1

Project discussion : Review and Action list
Teams meeting @VenuMadhav S , @Dhanasekar T

Discussion Points

  1. Parts list+ procurement status (Dhanasekar) - today
  2. top plate design, screen print design (Deeksha/shiva) - 3 days (we will provide screen print info)
  3. bottom plate design (Dhanasekar) - 2 days
  4. Mounting clamp/Frame (Dhanasekar) - 1 day
  5. -----------------will be completed by 03/06/2026(Wed)
  6. Procurement (Dhanasekar)- 1 week
  7. -----------------Will be completed by 08/06/2026 (Monday)
  8. Top plate Fabrication + Screen printing - 4 days
  9. -----------------Will be completed by 09/06/2026 (Monday)
  10. Mounting clamp/Frame fabrication/procurement (Dhanasekar) - 3days
  11. ----------------Will be completed by 09/06/2026 (Monday)
  12. flashing and debugging provisions(converter module) Venumadhav - today
  13. mDAQ3 i/f schematic design - 1 day
  14. mDAQ3 i/f PCB design - (single layer or w/o PTH ok. else dont fabricate)
  15. mDAQ3 i/f PCB fabrication - (single layer or w/o PTH ok. else dont fabricate)
  16. mDAQ3 faceplate design/retrofit - 1day
  17. -----------------Will be completed by 02/06/2026(Tuesday)
  18. ISP and Debug Box design - Venumadhav, Dhanasekar
  19. -----------------Will be completed by 03/06/2026(Wed)
  20. Custom Assembly (Share architecture and carry case design)- Surendra
  21. -----------------Will be completed by 03/06/2026(Wed), 09/06/2026 (Monday)
  22. Top plate assembly, bottom plate assembly
  23. -----------------Will be completed by 11/06/2026 (Thursday)
  24. Delivery Testing
  25. -----------------Will be completed by 12/06/2026 (Friday)
  26. All functional and performance testing to be completed by 05/06/2026 => Mohan, Jiban, Venumadhav, Thomas

Issues to resolve

  1. How to turn on MiniPC using panel control ?
    Ans : open mini PC and take connection outside or Using solenoid actuator, motor with Camshaft
  2. UPS will always on - leakage/sleep current - how long it will last - add addl. s/w parallel to existing - warranty issue with box open- contact vendor
    Ans: Open and take the connection to panel

BSH hand Delivery and Trial on 15/06/2026

@Dhanasekar T: Please check these date and inform Venu sir the optimised delivery date , arrange to inform customer

Updated by Thomas Joseph 3 months ago Actions #2

  • Status changed from New to In Progress

Updated by Thomas Joseph 3 months ago Actions #3

01/06/2026 (VM, DT, VK, BSN)

Sensor will receive by 22nd, hence despatch the unit with 100mV/g sensor, and replace once the 500mV/g sensor becomes available

Top Plate design => Deeksha, followup => Dhanasekar
Bottom plate design => Dhanasekar and Surendra => by 03/06/2026
ISP and Debug Box design - Venumadhav, Surendra => by 02/06/2026
Screen Print Design => Use from DDD
Mounting clamp/Frame design Dhanasekar, Surendra => by 03/06/2026
Digikey order => Dhanasekar by 02/06/2026 (URGENT) > add components for GW3.1, GW2.2, SAMAA5D2SOM_XPLD

mDAQ3 Device readiness => => by 05/06/2026
Complete I/F Schematic, create rework sheet => Venumadhav => by 02/06/2026
Complete Rework => Surendra => by 03/06/2026

Identify and order a speaker for use with mini PC audio out => Surendra, Venumadhav => => by 02/06/2026
Bring UPS LED to Top Plate (Charger status) => Venumadhav => by 05/06/2026
Use flexible ethernet cable inside carry case => Dhanasekar => => by 05/06/2026 (order by this date)

Update parts list with complete spec => Dhanasekar => => by 03/06/2026

Follow Redmine Tasks and update

Updated by Thomas Joseph 3 months ago · Edited Actions #4

  • % Done changed from 50 to 70

meeting (CH, JM, DT, SBN, TJ)

mDAQ3 rework sheet to upload in project folder
mDAQ3 assembly - completed

Flashing and debug
--Rs232 module to recive -
--Wiring diagram - Surendra to study
--modules on a common pcb with plug-in connector terminated
---get all components including box

get flexible LAN cable
panel cable assembly- Surendra to start

bottom plate and clamp fabrication - initiated

Top plate design and fab - follow up with Siva
mini PC testing - completed
buck module and UPS testing to complete on Monday

UPS+buck module+mini PC test to start on Tuesday

Updated by Thomas Joseph 3 months ago Actions #5

  • % Done changed from 70 to 90

Demo completed.