Task #3662
openProject Planning and Review
90%
Updated by Thomas Joseph 3 months ago
· Edited
Project discussion : Review and Action list
Teams meeting @VenuMadhav S , @Dhanasekar T
Discussion Points
- Parts list+ procurement status (Dhanasekar) - today
- top plate design, screen print design (Deeksha/shiva) - 3 days (we will provide screen print info)
- bottom plate design (Dhanasekar) - 2 days
- Mounting clamp/Frame (Dhanasekar) - 1 day
- -----------------will be completed by 03/06/2026(Wed)
- Procurement (Dhanasekar)- 1 week
- -----------------Will be completed by 08/06/2026 (Monday)
- Top plate Fabrication + Screen printing - 4 days
- -----------------Will be completed by 09/06/2026 (Monday)
- Mounting clamp/Frame fabrication/procurement (Dhanasekar) - 3days
- ----------------Will be completed by 09/06/2026 (Monday)
- flashing and debugging provisions(converter module) Venumadhav - today
- mDAQ3 i/f schematic design - 1 day
- mDAQ3 i/f PCB design - (single layer or w/o PTH ok. else dont fabricate)
- mDAQ3 i/f PCB fabrication - (single layer or w/o PTH ok. else dont fabricate)
- mDAQ3 faceplate design/retrofit - 1day
- -----------------Will be completed by 02/06/2026(Tuesday)
- ISP and Debug Box design - Venumadhav, Dhanasekar
- -----------------Will be completed by 03/06/2026(Wed)
- Custom Assembly (Share architecture and carry case design)- Surendra
- -----------------Will be completed by 03/06/2026(Wed), 09/06/2026 (Monday)
- Top plate assembly, bottom plate assembly
- -----------------Will be completed by 11/06/2026 (Thursday)
- Delivery Testing
- -----------------Will be completed by 12/06/2026 (Friday)
- All functional and performance testing to be completed by 05/06/2026 => Mohan, Jiban, Venumadhav, Thomas
Issues to resolve
- How to turn on MiniPC using panel control ?
Ans : open mini PC and take connection outside or Using solenoid actuator, motor with Camshaft - UPS will always on - leakage/sleep current - how long it will last - add addl. s/w parallel to existing - warranty issue with box open- contact vendor
Ans: Open and take the connection to panel
BSH hand Delivery and Trial on 15/06/2026
@Dhanasekar T: Please check these date and inform Venu sir the optimised delivery date , arrange to inform customer
Updated by Thomas Joseph 3 months ago
- Status changed from New to In Progress
Updated by Thomas Joseph 3 months ago
01/06/2026 (VM, DT, VK, BSN)
Sensor will receive by 22nd, hence despatch the unit with 100mV/g sensor, and replace once the 500mV/g sensor becomes available
Top Plate design => Deeksha, followup => Dhanasekar
Bottom plate design => Dhanasekar and Surendra => by 03/06/2026
ISP and Debug Box design - Venumadhav, Surendra => by 02/06/2026
Screen Print Design => Use from DDD
Mounting clamp/Frame design Dhanasekar, Surendra => by 03/06/2026
Digikey order => Dhanasekar by 02/06/2026 (URGENT) > add components for GW3.1, GW2.2, SAMAA5D2SOM_XPLD
mDAQ3 Device readiness => => by 05/06/2026
Complete I/F Schematic, create rework sheet => Venumadhav => by 02/06/2026
Complete Rework => Surendra => by 03/06/2026
Identify and order a speaker for use with mini PC audio out => Surendra, Venumadhav => => by 02/06/2026
Bring UPS LED to Top Plate (Charger status) => Venumadhav => by 05/06/2026
Use flexible ethernet cable inside carry case => Dhanasekar => => by 05/06/2026 (order by this date)
Update parts list with complete spec => Dhanasekar => => by 03/06/2026
Follow Redmine Tasks and update
Updated by Thomas Joseph 3 months ago
· Edited
- % Done changed from 50 to 70
meeting (CH, JM, DT, SBN, TJ)
mDAQ3 rework sheet to upload in project folder
mDAQ3 assembly - completed
Flashing and debug
--Rs232 module to recive -
--Wiring diagram - Surendra to study
--modules on a common pcb with plug-in connector terminated
---get all components including box
get flexible LAN cable
panel cable assembly- Surendra to start
bottom plate and clamp fabrication - initiated
Top plate design and fab - follow up with Siva
mini PC testing - completed
buck module and UPS testing to complete on Monday
UPS+buck module+mini PC test to start on Tuesday
Updated by Thomas Joseph 3 months ago
- % Done changed from 70 to 90
Demo completed.