Hours: 80:45

Date User Activity Issue Comment Hours Status Author Project Created Target version Tracker Week Category Finish Date Start Date Engr, %effort Team_Size Severity
20/07/2026 Sumanth D Expo Task #3726: Mumbai-Expo-July-2026 Expo 16:00 Analysis Started Sumanth D Ad-Hoc Design and Development 20/07/2026 06:03 AM Task 30 31/12/2026 01/01/2026 20%(need basis) 2 Actions
15/07/2026 Sumanth D Mechanical Assembly Task #3726: Mumbai-Expo-July-2026 Mechanical 6:00 Analysis Started Sumanth D Ad-Hoc Design and Development 15/07/2026 04:39 AM Task 29 31/12/2026 01/01/2026 20%(need basis) 2 Actions
13/07/2026 Thomas Joseph Expo Task #3726: Mumbai-Expo-July-2026 Preparation and discussion 1:30 Analysis Started Thomas Joseph Ad-Hoc Design and Development 13/07/2026 09:32 AM Task 29 31/12/2026 01/01/2026 20%(need basis) 2 Actions
10/07/2026 Sumanth D Design Task #3706: Flipkart - Cold room monitoring Block diagram for new design 1:00 In Progress Sumanth D Ad-Hoc Design and Development 10/07/2026 12:26 PM Task 28 31/12/2026 01/01/2026 20%(need basis) 2 Actions
10/07/2026 Thomas Joseph Demo Task #3726: Mumbai-Expo-July-2026 Expo Plan 1:00 Analysis Started Thomas Joseph Ad-Hoc Design and Development 10/07/2026 12:22 PM Task 28 31/12/2026 01/01/2026 20%(need basis) 2 Actions
08/07/2026 Sumanth D Testing Task #3706: Flipkart - Cold room monitoring Rework 6:00 In Progress Sumanth D Ad-Hoc Design and Development 08/07/2026 11:04 AM Task 28 31/12/2026 01/01/2026 20%(need basis) 2 Actions
08/07/2026 Thomas Joseph Development Task #3706: Flipkart - Cold room monitoring Discussion and production plan 1:30 In Progress Thomas Joseph Ad-Hoc Design and Development 08/07/2026 06:50 AM Task 28 31/12/2026 01/01/2026 20%(need basis) 2 Actions
08/07/2026 Thomas Joseph Development Task #3706: Flipkart - Cold room monitoring Measurement Support 2:00 In Progress Thomas Joseph Ad-Hoc Design and Development 08/07/2026 06:39 AM Task 28 31/12/2026 01/01/2026 20%(need basis) 2 Actions
07/07/2026 Thomas Joseph Development Task #3706: Flipkart - Cold room monitoring Circuit design and Team discussion 1:30 In Progress Thomas Joseph Ad-Hoc Design and Development 07/07/2026 07:54 AM Task 28 31/12/2026 01/01/2026 20%(need basis) 2 Actions
06/07/2026 Thomas Joseph Development Task #3706: Flipkart - Cold room monitoring Field testing support 3:00 In Progress Thomas Joseph Ad-Hoc Design and Development 06/07/2026 04:43 PM Task 28 31/12/2026 01/01/2026 20%(need basis) 2 Actions
06/07/2026 Thomas Joseph Design Task #3706: Flipkart - Cold room monitoring Design and Testing of TV3-485 2:30 In Progress Thomas Joseph Ad-Hoc Design and Development 06/07/2026 08:08 AM Task 28 31/12/2026 01/01/2026 20%(need basis) 2 Actions
04/07/2026 Thomas Joseph Development Task #3706: Flipkart - Cold room monitoring NTC to modbus in TV3 4:00 In Progress Thomas Joseph Ad-Hoc Design and Development 04/07/2026 10:11 AM Task 27 31/12/2026 01/01/2026 20%(need basis) 2 Actions
03/07/2026 Thomas Joseph Development Task #3706: Flipkart - Cold room monitoring Ciruit design and testing 2:00 In Progress Thomas Joseph Ad-Hoc Design and Development 03/07/2026 03:02 PM Task 27 31/12/2026 01/01/2026 20%(need basis) 2 Actions
02/07/2026 Thomas Joseph Design Task #3706: Flipkart - Cold room monitoring Circuit design for NTC to display and 485 converter 1:30 In Progress Thomas Joseph Ad-Hoc Design and Development 02/07/2026 03:47 PM Task 27 31/12/2026 01/01/2026 20%(need basis) 2 Actions
29/06/2026 Thomas Joseph Development Task #3706: Flipkart - Cold room monitoring NTC to 485 module testing 0:45 In Progress Thomas Joseph Ad-Hoc Design and Development 29/06/2026 04:40 PM Task 27 31/12/2026 01/01/2026 20%(need basis) 2 Actions
29/06/2026 Thomas Joseph Enquiry Task #3706: Flipkart - Cold room monitoring Customer discussion 0:30 In Progress Thomas Joseph Ad-Hoc Design and Development 29/06/2026 04:38 PM Task 27 31/12/2026 01/01/2026 20%(need basis) 2 Actions
26/06/2026 Thomas Joseph Enquiry Task #3706: Flipkart - Cold room monitoring Support and identifying issues 1:00 In Progress Thomas Joseph Ad-Hoc Design and Development 26/06/2026 06:53 PM Task 26 31/12/2026 01/01/2026 20%(need basis) 2 Actions
25/06/2026 Thomas Joseph Enquiry Task #3706: Flipkart - Cold room monitoring Support for Venumadhav for Data Capture 1:00 In Progress Thomas Joseph Ad-Hoc Design and Development 25/06/2026 08:22 AM Task 26 31/12/2026 01/01/2026 20%(need basis) 2 Actions
23/06/2026 Thomas Joseph Enquiry Task #3706: Flipkart - Cold room monitoring Support for Venumadhav for Data Capture 2:00 In Progress Thomas Joseph Ad-Hoc Design and Development 25/06/2026 06:28 AM Task 26 31/12/2026 01/01/2026 20%(need basis) 2 Actions
10/06/2026 Gowri G Development Task #3555: Software development and testing Software development and testing - Gone through the code and tested the bluetooth connectivity 8:00 Hold Gowri G Ad-Hoc Design and Development 11/06/2026 02:22 PM Task 24 31/12/2026 01/01/2026 20%(need basis) 2 Actions
29/05/2026 Gowri G Development Task #3555: Software development and testing Implemented the SPI in Tracker V2.1 for the reading ADXL registers and display the data on the tera term. 16:00 Hold Gowri G Ad-Hoc Design and Development 29/05/2026 05:17 PM Task 22 31/12/2026 01/01/2026 20%(need basis) 2 Actions
08/05/2026 Thomas Joseph Development Task #3555: Software development and testing ADXL345 Testing Support 2:00 Hold Thomas Joseph Ad-Hoc Design and Development 26/06/2026 04:20 PM Task 19 31/12/2026 01/01/2026 20%(need basis) 2 Actions