Hours: 36:00

Date User Activity Issue Comment Hours Status Author Project Created Target version Tracker Week Category Finish Date Start Date Engr, %effort Team_Size Severity
27/02/2026 Bhavani M Testing Task #3157: GW2.0 PCB Testing PCB testing 8:00 In Progress Bhavani M mDAQ4-1(Mid Range mDAQ)-Pilot 27/02/2026 07:13 AM Task 9 30/04/2026 02/01/2026 Thomas(20%), Venumadhav(100%),Dhilip(20%) 3 Actions
20/02/2026 Bhavani M Testing Task #3157: GW2.0 PCB Testing PCB Testing 8:00 In Progress Bhavani M mDAQ4-1(Mid Range mDAQ)-Pilot 20/02/2026 02:18 PM Task 8 30/04/2026 02/01/2026 Thomas(20%), Venumadhav(100%),Dhilip(20%) 3 Actions
20/02/2026 Bhavani M Testing Task #3157: GW2.0 PCB Testing Visual Inspection 4:00 In Progress Bhavani M mDAQ4-1(Mid Range mDAQ)-Pilot 20/02/2026 02:11 PM Task 8 30/04/2026 02/01/2026 Thomas(20%), Venumadhav(100%),Dhilip(20%) 3 Actions
30/01/2026 Bhavani M Testing Task #3157: GW2.0 PCB Testing GW2.0 PCB Testing 8:00 In Progress Bhavani M mDAQ4-1(Mid Range mDAQ)-Pilot 30/01/2026 05:35 AM Task 5 30/04/2026 02/01/2026 Thomas(20%), Venumadhav(100%),Dhilip(20%) 3 Actions
27/01/2026 Bhavani M Testing Task #3157: GW2.0 PCB Testing PCB testing 8:00 In Progress Bhavani M mDAQ4-1(Mid Range mDAQ)-Pilot 27/01/2026 02:57 PM Task 5 30/04/2026 02/01/2026 Thomas(20%), Venumadhav(100%),Dhilip(20%) 3 Actions
    (1-5/5)

    Also available in: CSV Atom