Task #3042
openTask #2985: Detailed Design
Test Plan Development and Approvals
Task #3042:
Test Plan Development and Approvals
Updated by Jagatheswaran J 4 months ago
- Status changed from New to In Progress
Updated by Jagatheswaran J 3 months ago
- % Done changed from 0 to 10
I started creating testcase based on the CRS.
Updated by Jagatheswaran J 3 months ago
- % Done changed from 10 to 80
Based on today’s discussion about the customer requirement scope, I have started creating the test cases and completed about 80%. I will complete the remaining test cases based on the current requirements. If the requirements change, I will update the test cases accordingly.
[[https://elpisit-my.sharepoint.com/:x:/g/personal/satish_sl_elpisitsolutions_com/IQCpyrn4UbBZRKagBSoOhmA_AQQOv-JOs5F7LPZcGIFk00c?e=qKUjHd]]
Updated by Jagatheswaran J 2 months ago
- % Done changed from 80 to 100
Updated by Sunder Venugopal about 2 months ago
- Related to Task #2989: Embedded SW-Development added
Updated by Sunder Venugopal about 2 months ago
- Precedes Task #2991: Wiring Diagram added
Updated by Sunder Venugopal about 2 months ago
- Due date changed from 27/03/2026 to 15/04/2026
- Start date changed from 20/03/2026 to 08/04/2026
- Follows Task #3168: USB Configuration Tool(Revision) added