Actions
Task #2968
open
TJ
DP
Task #2934: Detailed Design
SW-Development
Task #2968:
SW-Development
Start date:
09/01/2026
Due date:
13/02/2026 (26 days late)
% Done:
90%
Estimated time:
(Total: 0:00 h)
Spent time:
3:00 h (Total: 49:00 h)
Description
This is GW SW release 2.0
TJ Updated by Thomas Joseph 2 months ago
Please refer http://5.161.106.25:3000/issues/2952#note-3
TJ Updated by Thomas Joseph 2 months ago ยท Edited
@Channamallikarjuna Mattihalli , @DEVI PRIYAA : Include sub-tasks new/modified from GW2.0 s/w release
TJ Updated by Thomas Joseph 2 months ago
- Subtask #3026 added
TJ Updated by Thomas Joseph 2 months ago
Planned schedule is 9/1/2026 to 19/01/2026
TJ Updated by Thomas Joseph 2 months ago
- Subtask #3029 added
TJ Updated by Thomas Joseph 2 months ago
- Subtask #3030 added
TJ Updated by Thomas Joseph 2 months ago
- Subtask #3031 added
CM Updated by Channamallikarjuna Mattihalli 2 months ago
Hi VenuMadhavan,
When I discussed with Venu sir earlier, he asked me to work on the Modbus TCP task and informed in front of me and Devipriya that task 2968 and its subtasks would be handled by Devipriya.
So, kindly assign task 2968 and its subtasks to Devipriya.
Thank you.
VS Updated by VenuMadhav S 2 months ago
- Assignee changed from Channamallikarjuna Mattihalli to DEVI PRIYAA
TJ Updated by Thomas Joseph about 2 months ago
- Subtask #3161 added
DP Updated by DEVI PRIYAA about 2 months ago
- Status changed from New to In Progress
Venu madhav given the pin configurations for the SPI and other pins for PLCIO integration.Accordingly I am preparing the software build.
TJ Updated by Thomas Joseph about 2 months ago
- Subtask #3172 added
TJ Updated by Thomas Joseph 29 days ago
- Description updated (diff)
TJ Updated by Thomas Joseph 29 days ago
- Description updated (diff)
TJ Updated by Thomas Joseph 28 days ago
- Subtask #3254 added
TJ Updated by Thomas Joseph 28 days ago
- Subtask #3256 added
Actions