Discussion with Venumadhav
1. Controller PCB Super Cap mounting - orientation to change
2. Super cap - backup time analisys to do
3. schema - why super cap charging from 5.5V
4. Why RTC VBAT not switching - analysis to do
5. create views and share design folder for renaming
6. after renaming, continue sst placement
7. prepare section-wise costing all 4 PCBs
8. Design PLCIO connector PCB, do step mapping of all PCBs in enclosure - step1 - PLCIO normal orentation, step2 - PLCIO180deg rotated
9. Design of GW2.0 4G PCB with N58 in place of N720
10. assemble platform for GW2.0 with TV3.0 N720 PCB - Surendra to do
11. Order components for board bring-up assembly and mechanical fitment - 5 sets for PLCIO, connector, inerface, controller, enclosure
12. ISRO - List the activities at site, Send Surendra/Dhanasekar for new requirement support(Tracker demo for relay status)