Task #2917
open
SV
JJ
Task #2945: Testing
System Test Results and Reports
Task #2917:
System Test Results and Reports
Added by Sunder Venugopal 2 months ago. Updated about 1 month ago.
Description
Testing with Complete hardware, release version of embedded software, E-REMOS with all the accessories
SV Updated by Sunder Venugopal 2 months ago Actions #1
- Due date changed from 18/01/2026 to 20/01/2026
- Start date changed from 14/01/2026 to 15/01/2026
- Follows Task #2912: Hardware Readiness added
SV Updated by Sunder Venugopal 2 months ago Actions #2
- Follows Task #2915: EREMOS Development added
SV Updated by Sunder Venugopal 2 months ago Actions #3
- Precedes Task #2916: Proto 1 Delivery to Chola added
SV Updated by Sunder Venugopal 2 months ago Actions #4
- Due date changed from 20/01/2026 to 18/01/2026
SV Updated by Sunder Venugopal 2 months ago Actions #5
- Due date changed from 18/01/2026 to 19/01/2026
- Follows Task #2913: Test Plan Development and Approvals added
TJ Updated by Thomas Joseph 2 months ago Actions #6
- Parent task set to #2945
TJ Updated by Thomas Joseph 2 months ago Actions #7
- Description updated (diff)
SV Updated by Sunder Venugopal 2 months ago Actions #8
- Follows Task #2911: PLC MODBUS mapping from Chola on Siemens PLC added
TJ Updated by Thomas Joseph about 2 months ago Actions #9
- Due date changed from 19/01/2026 to 21/01/2026
- Start date changed from 15/01/2026 to 19/01/2026
SV Updated by Sunder Venugopal about 2 months ago Actions #10
- Due date changed from 21/01/2026 to 26/01/2026
- Start date changed from 19/01/2026 to 22/01/2026
SV Updated by Sunder Venugopal about 2 months ago Actions #11
- Due date changed from 26/01/2026 to 21/01/2026
- Start date changed from 22/01/2026 to 19/01/2026
SV Updated by Sunder Venugopal about 2 months ago Actions #12
- Due date changed from 21/01/2026 to 20/01/2026
JJ Updated by Jagatheswaran J about 2 months ago Actions #13
- % Done changed from 0 to 100
JJ Updated by Jagatheswaran J about 2 months ago Actions #14
- % Done changed from 100 to 0
SV Updated by Sunder Venugopal about 2 months ago Actions #15
- Follows Task #2952: Embedded SW-Development added
SV Updated by Sunder Venugopal about 2 months ago Actions #16
- Follows Task #3028: USB Factory Configuration added
SV Updated by Sunder Venugopal about 2 months ago Actions #17
- Due date changed from 20/01/2026 to 23/01/2026
- Start date changed from 19/01/2026 to 22/01/2026
- Follows Task #2941: Detailed Design added
TJ Updated by Thomas Joseph about 2 months ago Actions #18
- Due date changed from 30/01/2026 to 10/02/2026
- Start date changed from 29/01/2026 to 09/02/2026
TJ Updated by Thomas Joseph about 2 months ago Actions #19
- Follows deleted (Task #3028: USB Factory Configuration)
TJ Updated by Thomas Joseph about 1 month ago Actions #20
- Follows deleted (Task #2915: EREMOS Development)
TJ Updated by Thomas Joseph about 1 month ago Actions #21
- Follows deleted (Task #2941: Detailed Design)
TJ Updated by Thomas Joseph about 1 month ago Actions #22
- Follows deleted (Task #2952: Embedded SW-Development)
TJ Updated by Thomas Joseph about 1 month ago Actions #23
- Precedes deleted (Task #2916: Proto 1 Delivery to Chola)
TJ Updated by Thomas Joseph about 1 month ago Actions #24
- Due date changed from 28/01/2026 to 26/01/2026
- Start date changed from 27/01/2026 to 22/01/2026
JJ Updated by Jagatheswaran J about 1 month ago Actions #25
- % Done changed from 0 to 20
Observed Issues:
1.Data posting takes 1. 17 minutes to update on the dashboard.
2.On the dashboard, current parameters (R and Y phase) are not updating properly.
3.After one hour of continuous data posting, a checksum error occurs. Device resumes posting only after a power cycle.
4.Graph is not updating properly.
5.Report sending via email is not working.
I have tested only Modbus continuous posting,Modbus connectivity and parameter updates. testing is still in progress.