Task #2917
openTask #2945: Testing
System Test Results and Reports
Task #2917:
System Test Results and Reports
Added by Sunder Venugopal 4 months ago. Updated 3 months ago.
Start date:
22/01/2026
Due date:
26/01/2026 (about 3 months late)
% Done:
20%
Estimated time:
Spent time:
Description
Testing with Complete hardware, release version of embedded software, E-REMOS with all the accessories
Updated by Sunder Venugopal 4 months ago
Actions
#1
- Due date changed from 18/01/2026 to 20/01/2026
- Start date changed from 14/01/2026 to 15/01/2026
- Follows Task #2912: Hardware Readiness added
Updated by Sunder Venugopal 4 months ago
Actions
#2
- Follows Task #2915: EREMOS Development added
Updated by Sunder Venugopal 4 months ago
Actions
#3
- Precedes Task #2916: Proto 1 Delivery to Chola added
Updated by Sunder Venugopal 4 months ago
Actions
#4
- Due date changed from 20/01/2026 to 18/01/2026
Updated by Sunder Venugopal 4 months ago
Actions
#5
- Due date changed from 18/01/2026 to 19/01/2026
- Follows Task #2913: Test Plan Development and Approvals added
Updated by Thomas Joseph 4 months ago
Actions
#6
- Parent task set to #2945
Updated by Thomas Joseph 4 months ago
Actions
#7
- Description updated (diff)
Updated by Sunder Venugopal 4 months ago
Actions
#8
- Follows Task #2911: PLC MODBUS mapping from Chola on Siemens PLC added
Updated by Thomas Joseph 4 months ago
Actions
#9
- Due date changed from 19/01/2026 to 21/01/2026
- Start date changed from 15/01/2026 to 19/01/2026
Updated by Sunder Venugopal 4 months ago
Actions
#10
- Due date changed from 21/01/2026 to 26/01/2026
- Start date changed from 19/01/2026 to 22/01/2026
Updated by Sunder Venugopal 4 months ago
Actions
#11
- Due date changed from 26/01/2026 to 21/01/2026
- Start date changed from 22/01/2026 to 19/01/2026
Updated by Sunder Venugopal 4 months ago
Actions
#12
- Due date changed from 21/01/2026 to 20/01/2026
Updated by Jagatheswaran J 4 months ago
Actions
#13
- % Done changed from 0 to 100
Updated by Jagatheswaran J 4 months ago
Actions
#14
- % Done changed from 100 to 0
Updated by Sunder Venugopal 4 months ago
Actions
#15
- Follows Task #2952: Embedded SW-Development added
Updated by Sunder Venugopal 4 months ago
Actions
#16
- Follows Task #3028: USB Factory Configuration added
Updated by Sunder Venugopal 4 months ago
Actions
#17
- Due date changed from 20/01/2026 to 23/01/2026
- Start date changed from 19/01/2026 to 22/01/2026
- Follows Task #2941: Detailed Design added
Updated by Thomas Joseph 3 months ago
Actions
#18
- Due date changed from 30/01/2026 to 10/02/2026
- Start date changed from 29/01/2026 to 09/02/2026
Updated by Thomas Joseph 3 months ago
Actions
#19
- Follows deleted (Task #3028: USB Factory Configuration)
Updated by Thomas Joseph 3 months ago
Actions
#20
- Follows deleted (Task #2915: EREMOS Development)
Updated by Thomas Joseph 3 months ago
Actions
#21
- Follows deleted (Task #2941: Detailed Design)
Updated by Thomas Joseph 3 months ago
Actions
#22
- Follows deleted (Task #2952: Embedded SW-Development)
Updated by Thomas Joseph 3 months ago
Actions
#23
- Precedes deleted (Task #2916: Proto 1 Delivery to Chola)
Updated by Thomas Joseph 3 months ago
Actions
#24
- Due date changed from 28/01/2026 to 26/01/2026
- Start date changed from 27/01/2026 to 22/01/2026
Updated by Jagatheswaran J 3 months ago
Actions
#25
- % Done changed from 0 to 20
Observed Issues:
1.Data posting takes 1. 17 minutes to update on the dashboard.
2.On the dashboard, current parameters (R and Y phase) are not updating properly.
3.After one hour of continuous data posting, a checksum error occurs. Device resumes posting only after a power cycle.
4.Graph is not updating properly.
5.Report sending via email is not working.
I have tested only Modbus continuous posting,Modbus connectivity and parameter updates. testing is still in progress.